On Tue, 3 Oct 2000 14:53:31 -0400 dg50@daimlerchrysler.com writes:
> OK, here's something else to chew on.
>
>
> But a back-of-the-napkin calculation says that a 200'X200' pad, at a
> depth
> of 4", works out to roughly 40 cubic yards of concrete. At roughly
> 10 cubic
> yards of concrete per truckload, and roughly $100 per truckload,
> then that
> pad costs $4000. Still not chump change, but a 200 sqft pad is a
> decent
> sized skidpad....
Canada shure has some cheap concrete... it's @ $60.00 a yard in PA. If
doing a large project (autox site) you could probably get it cheaper
though.
My scratch paper figures: 200'x200' is 40,000sf.
40,000 divided by 80 (sf
per yard at 4" thick) is 500
500yards x $60 is $30,000
EC