Richard scribes:
> however, the contractor didn't double up the last complete 2x12
> adjacent to the repaired hole, but did butt a header into it. an
> architect friend of ours looked at it and advised me to double up the
> 2x12. i have got the new joist in place, and am now wondering just how
> many screws or nails i should use, at what intervals, to secure the
> two 2x12s together. any suggestions, anyone?
---------------------------------------------------------------------
Coat the mating surfaces of the (new) sister and the existing joist. Clamp
them together. Then use "premium deck screws" (that's what we call 'em here
in the midwest) at a 6" or so spacing, staggered, to permanently clamp the
two load bearing joist's together *before* the glue dries.
bsh
///