Gosh darn its nice to have you back for some of that good old confusing,
hair pulling math gibberish. Did you "play and play"? just checking.

Jonathan


> Jon, now you need to complete the list activty. By that, I mean make a
flow
> diagram showing what has to be done in order to begin or complete a task,
ie
> precursors and post cursors. That is the systems engineering way and also
MS
> Project way. Plus you can weight the activities to determine the relative
> importance of any activity so you know which ones to beat on first. Then
you
> can apply Pareto's law: 20 percent of a pile of things will cause you 80
> percent of your grief (works for other things also). Then determine the
most
> inportant of the 20 percent and beat on it till it is done. Shoot, this is
> how I run my life, I do this everyday.....yeah right...
>
> mayf